Demolition Phase Nears Completion

The demolition phase is now nearing completion at our site in the heart of Wembley, located on the famous Wembley Way.

Over the past 12 weeks, the team has carried out controlled, floor-by-floor demolition alongside a significant programme of enabling works. These have included sheet piling, the construction of a substantial attenuation tank, and major deep-level drainage diversion works.

This programme of works marks an important milestone in the project, preparing the site for the next stage of development.

With demolition and enabling works drawing to a close, the project will progress into piling before moving into the main construction phase. This marks the next step in the site’s development as work continues to progress.