Project Profile: Asda Kettering

Client
Asda
Date of completion
October 2018
Value
n/a
Kettering main
kettering 2

Scope of works

  • The demolition of the existing sales shop to facilitate the build of a new kiosk and a new control room 

  • Removal of the concrete forecourt surface in order to extract the six existing fuel tanks

  • Installation of two new 75,000 litre fuel tanks with new fuel lines, a new 10,000 litre class 1 interceptor and four new pump islands 

  • Refurbishment of the existing car wash and existing jet wash bay, installing a new jet wash machine

kettering 3

Key points 

  • The site team overcame the challenge of poor ground conditions with piled foundations for the canopy and a cofferdam for the new tank 

  • The project was complete with a new canopy and a new forecourt which was constructed with both concrete and tarmac 

  • The project was successfully completed and handed over to our enthusiastic client who was once again delighted with Toureen's high standard of workmanship; "Another great scheme landed by Bryan and his team, Nick has been a fantastic Site Manager, the project finished on time which was a great effort considering the ground conditions we had on site." 

Toureen Retail was appointed by Asda to deliver the complete knock-down and re-build of their Kettering petrol filling station